National Highways Wing |
Projects |
Draft Annual Plan amounting to Rs. 320.68 crore for improvement of NHs works has been forwarded to GOI for approval. Approval is awaited. The Plan envisages improvement of NHs on the following fields during the year 2012-13. |
Widening to two Lane |
41.34 km |
Strengthening of existing pavement |
1.48 km |
Improvement of Riding quality |
123.16 km |
Re-Construction/Rehabilitation of Bridge (Nos.) |
9 Nos. |
|
Improvement of NH to two lane standard under Special Project |
Improvement of 221.960 km of NHs as detailed below are under implementation. |
Sl. No. |
NH Corridor |
NH |
Chainage |
Length in km |
1. |
Kolabira-Kuchinda-Bhojpur |
200 |
89-104 & 117-131 |
29.00 |
2. |
Borigumma-Nawarangpur |
201 |
0.0 to 25.0 |
25.00 |
3. |
Koksara-Bhawanipatna |
201 |
95.0 to 112.1 & 113.8-143.4 |
46.71 |
4. |
Bangamunda-Titilagarh |
217 |
164.0 to 189.0 |
25.00 |
5. |
Baliguda-Daringibadi |
217 |
329.0 to 375.0 |
46.00 |
6. |
Madhapur-Purunakatak |
224 |
159.0 to 184.260 |
25.26 |
7. |
Telibandha-Manamunda |
224 |
224.0 to 269.0 |
25.00 |
|
|
|
Total |
221.960 |
|
|
|