Sl. No. |
Name of the Work |
Name of Deptt. |
Cost of the Project (Value of Work Done) Rs. In Lakhs |
Completion Period |
1. |
Bridge over river Sonegarh on Baragarh-Balangir Road. |
E.E. Balangir (R&B) Division |
133.70 |
89-90 |
2. |
Bridge over Tel on Balangir Bhawanipatna Road. |
E.E. Bhawanipatna (R&B) Division |
396.11 |
92.93 |
3. |
Bridge over Bada Nallah-on 132 K.V. Line diversion due to Minor Irrigation Project |
E.E. Rayagada (R&B) Division |
287.36 |
93-94 |
4. |
Bridge over Kolab near Pitaguda on Similiguda-Handiput Road |
E.E.Koraput (R&B) Division |
149.76 |
93-94 |
5. |
Improvement to Jharsuguda-Kanaktora Road. (Reach 1 from 0/0 K.M. to 7/0 K.M.) (Reach-1) |
E.E.Sambalpur (R&B) Division |
80.93 |
93-94 |
6. |
Extended Span of Brahmani Bridge on Dhenkanal-Kamakhyanagar Road. |
E.E. Dhenkanal (R&B) Division |
61.05 |
93-94 |
7. |
Bridge Over River Mahanadi at Mundali weir |
E.E. Jagatsinghpur (R&B) Division |
434.15 |
93-94 |
8. |
H.L. Bridge over river Budhabalanga at Nakharaghat on Thakurmunda-Udala-Rupsa Road. |
E.E. Mayurbhanja (R&B) Division |
109.30 |
93-94 |
9. |
Bridge over Dahikhia on Sunamuhin-Satpada Road (TENDER) |
E.E. Puri (R&B) Division |
68.17 |
94-95 |
10. |
Approach Road to Dahikhia Bridge on Sunamuhin-Satpada Road. |
E.E.Puri (R&B) Division |
23.07 |
94-95 |
11. |
Bridge over Sandhi Nallah on high embankment of 132 K.V. Line Road. |
E.E. Paralakhemundi (R&B) Division |
93.41 |
94-95 |
12. |
Bridge over Kolab (Saberi) on Govindpali-Salim Road. |
E.E. Jeypur (R&B) Division |
306.72 |
94-95 |
13. |
Protection work such as Epoxy treatment & Grouting to “TEL” Bridge at Bhawanipatna. |
E.E. Bhawanipatna (R&B) Division |
62.62 |
94-95 |
14. |
Bridge over Khola creek at Rajnagar on Talchua Rajnagar Embankment. |
E.E. Kendrapara (R&B) Division |
78.51 |
94-95 |
15. |
Bridge over Gagua creek at Babar on Babar-Zambu Road. |
E.E. Kendrapara (R&B) Division |
64.42 |
94-95 |